The customer's problem
At the Würth representative office in Berlin, the existing building automation was to be modernized and transferred to a new technical base. For this purpose, ten controllers had to be migrated from the previous Honeywell system XL500 to XL800. At the same time, existing system functions and field signals as well as the existing control cabinets had to be integrated into the new system structure.
A particular challenge was to take over the heating, ventilation, and building management functions in the existing building and to adjust the system and control cabinet documentation accordingly. In addition, material procurement, conversion, commissioning, and remaining residual services had to be coordinated.
Solution by AUCOTEAM
AUCOTEAM took over the technical planning and complete implementation of the DDC migration. The existing substations were converted to freely programmable Honeywell XL800 automation stations and equipped with the required input and output modules.
The scope of work included the design of the control loops, the programming and parameterization of the automation stations, as well as the necessary electrical installation and wiring work in the existing control cabinets. Afterwards, the modernized substations were connected to the existing control center, commissioned, and properly balanced.
In addition, AUCOTEAM updated the control diagrams, layout plans, and control cabinet documents. After instructing the operating personnel, the structured handover of documentation, data backups, and digital circuit diagram files took place.
Key Features of the AUCOTEAM Solution
The special feature lay in the comprehensive modernization of the existing building automation. AUCOTEAM combined the technical planning, programming, and control cabinet adjustment with commissioning and documentation into a seamless overall solution.
Existing heating, ventilation, and building management functions were integrated into the new automation structure without completely replacing the existing system environment. At the same time, the modernized substations were connected to the existing central control unit.
The updated switchgear and system documents, data backups, and the newly digitized wiring diagrams provided create a comprehensible basis for operation, maintenance, and future technical adjustments.